The Boral Geelong Clinker Grinding Facility, situated in North Shore Geelong, is a crucial component of Boral’s cement production, boasting a processing capacity of up to 1.3 million tonnes annually.

Its electrical installation is fundamental to its operations. Designed for continuous operation, the electrical infrastructure supports a 24-hour, 50-week-per-year schedule, ensuring consistent cement production.

Gordon McKay’s scope of work included:

  • Installing five high-voltage (HV) transformers, along with their switchgear, metering, and dedicated switch rooms. It also included the complete low-voltage distribution network, powering motors, conveyors, cooling systems, silos, and all facility lighting
  • Installing a comprehensive lighting system to enable 24-hour facility operation while preventing light spill onto surrounding properties. It also included all cable routing and installation, encompassing cable ladders and conduit
  • Installing a communications system, including all cabling and equipment installed via underground conduits, cable ladders, and conduits, now supports the plant’s advanced PLCs and SCADA automation, vital for performance and efficiency
  • The complete wiring and connection of the dust suppression and noise reduction systems within the plant
  • Commissioning
  • Development of ITPs and quality assurance frameworks

Gordon McKay was successful in the installation and commissioning of electrical and control equipment ensuring Boral could increase their cement production.

Boral-cement
Client
Boral Cement
Location
North Shore, Geelong
Completed
February 2023
Sector
Manufacturing
Services / products

High voltage installation
Industrial light and power
Communications